Dear Osman,
This is to update you that
the MER-1 and MER-2 Shutdown has been completed successfully. FollowingTHe following issues were observed during the shutdown. There was no major impact reported on any system.
MER-1
One STS got faulty during
the MER-1 Shutdown and the same has been replaced immediately in presence of AHB IT personnel.
FollowingThe following maintenance work was accomplished during the shutdown.
• MER-1 UPS PPM completed by MDS
MER-1 PDU PPM completed by Al Mafoor
Defective temperature transducer replaced by Al Mafoor
PPM for the LV system completed by Inspire In-housein-house team.
BKG has rectified the CT wrong connection issue, it was a legacy issue

MER-2
One STS got faulty during
the MER-2 shutdown and the same has been replaced immediately in presence of AHB IT personnel.
• MER-2 UPS PPM completed by MDS
• MER-2 PDU PPM completed by Al Mafoor
• PPM for the LV system completed by Inspire
In-housein-house team.
• BKG has rectified the CT wrong connection issue, it was a legacy issue


All reports shall be submitted to you soon.

The text above was approved for publishing by the original author.

Previous       Next

Jetzt kostenlos testen

Bitte geben Sie Ihre Nachricht ein.
Bitte wählen Sie die zu korrigierende Sprache.

Probieren Sie unsere iPhone/iPad-App fürs Korrekturlesen aus!

eAngel.me

eAngel.me is a human proofreading service that enables you to correct your texts by live professionals in minutes.