Dear Osman,
This is to update you that the MER-1 and MER-2 Shutdown has been completed successfully. FollowingTHe following issues were observed during the shutdown. There was no major impact reported on any system.
MER-1
One STS got faulty during the MER-1 Shutdown and the same has been replaced immediately in presence of AHB IT personnel.
FollowingThe following maintenance work was accomplished during the shutdown.
• MER-1 UPS PPM completed by MDS
• MER-1 PDU PPM completed by Al Mafoor
• Defective temperature transducer replaced by Al Mafoor
• PPM for the LV system completed by Inspire In-housein-house team.
• BKG has rectified the CT wrong connection issue, it was a legacy issue
MER-2
One STS got faulty during the MER-2 shutdown and the same has been replaced immediately in presence of AHB IT personnel.
• MER-2 UPS PPM completed by MDS
• MER-2 PDU PPM completed by Al Mafoor
• PPM for the LV system completed by Inspire In-housein-house team.
• BKG has rectified the CT wrong connection issue, it was a legacy issue
All reports shall be submitted to you soon.