Dear,
Kindly note that we had submitted a time schedule for one year (365 working days ) with our technical proposal as attached. , pleasePlease find attached here with for your review and . We shiftshifted the start date (mobilization ) to 10/01/2021.
This time schedule according to activity describedescribed in our technical proposal and most of site are ready in same time , so this time schedule is very compressed .
So, kindly re send LOA after correctcorrecting the execution period from 5 monthmonths to 12 monthmonths excluding stop date du to hajj season .
In additionaladdition, the roofing ballast according to specification SECTION 07 56 00 (PROTECTED BITUMINOUS ROOFING ) is gravel and we consider the tiles which mentioned in other documents as walk way only and our technical proposal was based on that .
The text above was approved for publishing by the original author.
Previous
     
Next
Gehen Sie einfach in Ihren Posteingang, klicken Sie auf den Bestätigungslink, den wir Ihnen gesendet haben, und Sie bekommen den korrigierten Text zurück. Wenn Sie mehr E-Mails korrigiert haben wollen, können Sie einfach:
Oder